Busselton West Street Pipe Alignment

Closed 29 Nov 2015

Opened 23 Nov 2015

Overview

The Water Corporation is proposing to construct  approximately 840 metres of  DN450 pressure main from the West Street Wastewater Pump Station to the intersection of Frederick and Fairlawn Streets in Busselton.

A section of the pipeline passes through the buffer of a Conservation Category Wetland known as New River.  The Water Corporation is proposing trenchless construction techniques in this area to minimise impacts.

What happens next

Following the seven day public comment period and consideration of any comments received, the EPA will decide whether or not this proposal requires environmental impact assessment and, if so, what level of assessment will be applied.

The Chairman's decisions on level of assessment are released each Monday on the EPA's website.

Areas

  • All of Western Australia

Audiences

  • Public

Interests

  • Seven-day comment on referrals