Scarborough Project Nearshore Component

Closed 15 Jan 2019

Opened 9 Jan 2019

Overview

The Proposal would include the following activities:

shore crossing site preparation including installation of temporary facilities along the shoreline at the Pluto LNG Facility to facilitate the installation of the trunkline in shallower depths

preparation works associated with the installation of the trunkline including dredging and associated spoil disposal at existing spoil grounds

trunkline installation (about 32.7 kilometres long within State waters)

shore crossing site reinstatement

rock supply and dumping/sand supply and backfilling of the trench with sand and/or rock to protect the trunkline

pre-commissioning testing

commissioning and operation

decommissioning.

Why your views matter

At this initial stage of the EIA process, comment is simply sought on whether or not the EPA should assess a proposal and, if so, what level of assessment is considered appropriate.

What happens next

Following the seven day public comment period and consideration of any comments received, the EPA will decide whether or not this proposal requires environmental impact assessment and, if so, what level of assessment will be applied.

The EPA's decisions on level of assessment are released each Monday on the EPA's website.

Areas

  • All of Western Australia

Audiences

  • Public

Interests

  • Seven-day comment on referrals